Cost Analysis


Background Information
      A Comparison of Costs for Modern Subway Construction in North America
Spadina and North Yonge Cost Breakdown
      TTC Spadina Extension Cost Estimates
      TTC Yonge North Extension Cost Estimates
      Station Costs
      Track Costs
      Engineering Costs
      Subway Yard Costs
      Rolling Stock Costs
      Property Acquisition Costs
      Contingency Costs
Cost Estimates for Stage One of Construction: Cityplace (Spadina) to Wynford (Eglinton)
      Stations
      Track
      Costs
Cost Estimates for Stage Two of Construction: Cityplace (Spadina) to Dundas West
      Stations
      Track
      Costs
Cost Estimates for Stage Three of Construction: Wynford (Eglinton) to Sheppard/Don Mills
      Stations
      Track
      Costs
Cost Estimates for Stage Four of Construction: Dundas West to Pearson Airport
      Stations
      Track
      Costs
Combined Cost for All Stages

Background Information

Subway construction is understood to be a costly venture, but there are various factors that contribute to the cost. Beyond the obvious costs of labour and materials, costs can vary depending on methods of construction, as well as geology and other local factors. Thus, costs for similar projects can vary dramatically. The following is a list of projects that have been constructed or proposed in the last ten years. Due to a difference in labour laws and regulations in Europe, the data has been limited to recent North American construction, where although laws may differ slightly, no major variations occur.


A Comparison of Costs for Modern Subway Construction in North America

City Project Status Cost (CDN, in Millions) Length (km) Cost/km (in millions) Method
New York 2nd Avenue Subway Under Construction 4964.34 3.7 1342 Tunnelled131
Boston Blue Line to Red Line Proposed 306 0.64 478 Tunnelled16
Toronto Yonge North Extension Proposed 2400 6.8 353 Tunnelled174
Los Angeles Purple Line Extension Proposed 6222 20 311 Tunnelled106,107
Toronto Spadina Extension Under Construction 2600 8.6 302 Tunnelled137
Vancouver Millennium Line Proposed 2800 12 233 Tunnelled24
Montreal Blue Extension to Pie IX Proposed 170 1 170 Tunnelled73
Montreal Orange Extension to Bois Franc from Cote Vertu Proposed 340 2.2 155 Tunnelled73
Montreal Blue Extension to Anjou Proposed 775 5.1 152 Tunnelled73
Washington Silver Line Under Construction 2754 18.6 148 Primarily At Grade169,14
Toronto Sheppard Subway Complete (2002) 934 6.4 146 Tunnelled37
Montreal Orange Extension to Montmorency Complete (2007) 745 5.2 143 Tunnelled90
Chicago Orange Line Extension Proposed 453.9 3.6 126 At Grade38
Vancouver Canada Line Complete (2009) 2054 19.1 108 Mixed142
Chicago Red Line Extension Proposed 896.58 8.5 105 At Grade39
Chicago Yellow Line Extension Proposed 268.26 2.6 103 At Grade40
Boston Blue Line to Lynn Proposed 611 7.2 85 At Grade/Elevated65,127

Two cities stand out when compared to the cost of projects in Toronto, which have more than doubled in cost estimates for the past decade. Montreal: and New York.

On the cheaper end of construction, Montreal should be studied as to why it is able to deliver subway at a substantially lower cost per kilometre than we have been able to in Toronto.


Montreal's Two-Train Subway Tunnels

In Montreal, we have the benefit of seeing both a recently constructed project (the orange line to Montmorency in Laval) as well as a number of proposed projects. Costs range from $143 million to $173 million per kilometre, a cost half that of modern subways in Toronto such as the Spadina extension and the North Yonge extension. Unlike several other cheaper projects that have been constructed or proposed in North America, Montreal’s subway construction is entirely tunnelled, with no sections at grade. The Laval extension in particular had the challenge of tunnelling under the Rivière des Prairies, and still was able to complete construction at a cost of $143 million/km. As nice as it would be to be able to build the Downtown Relief Line for this sort of cost, unfortunately it is not feasible. As well as being of a different geology than the City of Toronto67, a more important factor for Montreal is the width of their trains. Due to thinner trains, Montreal is able to construct their system using one large bored tunnel with multiple tracks rather than being forced to construct two smaller tunnels54. This can reduce tunnelling costs substantially with half as much tunnel required for construction.

On the other end of the spectrum, New York suffers from significantly higher tunnelling and construction costs, with the MTA stating the following in regards to the costs of the Second Avenue Subway.

Our partners in the contracting community tell us that they are forced to charge more for our projects to protect against the perceived risks of working with the MTA and to compensate for the difficult environment of working around service and the complexity of each project. In addition, construction industry practices in New York tend to increase costs. As an example, tunnelling for the expansion projects has cost between three and six times as much as similar projects in Germany, France and Italy162

Because other cities may be substantially cheaper or costlier than Toronto, their estimates are not as relevant to the costing of the Downtown Relief Line, and are simply provided for the sake of comparison. Because we have recent construction cost estimates in Toronto, we can use those as a base for estimations of the cost of the Downtown Relief Line with much greater accuracy.



Spadina and North Yonge Cost Breakdown

The Spadina Subway has begun construction on an extension to Vaughan Metropolitan Centre that is projected to cost $2.6 billion148. In 2008, the TTC released a report breaking down costs of the line. Though the total at the time was $2.1 billion, the details allow for a number of cost estimates to be derived. Most of these costs can be broken down to a per kilometre rate, which can be used as a baseline for Downtown Relief Line estimates.



TTC Spadina Extension Cost Estimates149

Project Element Cost ($ 2006) Cost / km % of Project
Sheppard West Station $52,221,136 N/A 2.5%
Finch West Station $80,792,624 N/A 3.9%
York University Station $72,627,126 N/A 3.5%
Steeles West Station $100,192,532 N/A 4.8%
Highway 407 Station $80,278,726 N/A 3.8%
Vaughan Metropolitan Centre Station $78,964,512 N/A 3.8%
Running Structure (Tunnelling & Cut/Cover) $484,206,187 $56,303,045 23.2%
Utilities (excludes stations) $19,834,813 $2,306,374 0.9%
Trackwork $64,345,820 $7,482,072 3.1%
Power (including DC Traction Power) $30,371,682 $3,531,591 1.5%
Train Control (Signals) $33,206,910 $3,861,269 1.6%
Supervisory Control $24,451,412 $2,843,187 1.2%
Wilson Yard Modifications $84,280,000 N/A 4.0%
Project Engineering, Management, Geotechnical, Permits, Insurance, Etc. $301,443,370 $35,051,555 14.4%
Contingency (26%) $399,412,465 $46,443,310 19.1%
Property & Miscellaneous $99,737,000 $11,597,326 4.8%
GST Rebate ($117,248,793) ($13,633,581) -5.6%
Revenue Vehicles (56 Subway Cars) $201,712,000 $23,454,884 9.6%
TOTAL $2,090,829,522 $243,119,712 100.0%

The estimates of the Yonge subway extension have also been released, though in less detail.



TTC North Yonge Extension Cost Estimates173

Project Element Cost Cost/km % of Project
Finch Improvements $5,000,000

N/A

0.2%

Cummer/Drewry Station

$70,000,000

N/A

2.9%

Steeles Station

$195,000,000

N/A

8.1%

Clark Station

$70,000,000

N/A

2.9%

Royal Orchard Station

$65,000,000

N/A

2.7%

Langstaff/Longbridge Station

$85,000,000

N/A

3.5%

Richmond Hill Centre Station

$160,000,000

N/A

6.7%

Tunnels, special structures and operating systems

$600,000,000

$88,235,294

25.0%

Subway Trains

$240,000,000

$35,294,118

10.0%

Storage and Maintenance Facilities for subway trains

$110,000,000

N/A

4.6%

Engineering and other costs

$675,000,000

$99,264,706

28.1%

Property

$125,000,000

$18,382,353

5.2%

TOTAL

$2,400,000,000

$352,941,176

100.0%


Station Costs

Since the initial release of the Spadina extension, the cost of the stations has been re-estimated, and has gone up.

Station Initial Estimate (2006) Revised Estimate (2010) Cost Escalation
Sheppard West $52,221,136 $102,000,000152 95.3%
Finch West $80,792,624 $134,000,000150 65.9%
York University $72,627,126 $115,000,000155 58.3%
Steeles West $100,192,532 $145,000,000153 44.7%
Highway 407 $80,278,726 $134,000,000151 66.9%
Vaughan Metropolitan Centre $78,964,512 $177,000,000154 124.2%
TOTALS $465,076,656 $807,000,000 73.5%

Though it may appear that stations ballooned over their expected cost by 73.5%, it isn’t quite that simple. Initial cost estimates were made prior to station design. In the revised estimates, it establishes what was actually budgeted for in the most recent $2.6 billion estimate. The total costs of the budgeted stations is $610.2 million, making the stations cost 32% over what the specific designs were budgeted for.

These increases are not insignificant, and cast severe doubts upon the estimates of the Yonge line. Using the Spadina Line’s higher station costs then, we learn that station costs can be broken down as such:

Type of Station Cost of Construction
No Bus Terminal or Commuter Parking $102-115M
Bus Terminal and Commuter Parking $134-145M
Terminal Stations $177M

To determine the cost of above ground and elevated stations, the easiest method is to compare with the proposed Chicago extensions, where the high end estimate for at grade stations is approximately $25 million for a terminal station and $31 million for inline elevated stations. To be on the safe side, we will estimate a cost of $30 million for an average at grade station and $40 million for an elevated station, not including the cost of parking.

Though cost estimation can fluctuate depending on other factors such as the depth and complexity of the station, these figures can provide a good base for the determination of station costs for the Downtown Relief Line.


Track Costs

Though station costs are a large part of the project, calculating the cost of building tunnels, laying track, and providing the necessary support structures and systems necessary for operation also play a major role.


The Subway Emerges From a Tunnel to an Open Cut

In the Spadina line, the combination of factors that go into track building totalled $76.3 million per km. The Yonge line has it projected at $88.2 million per km. When considering that the Spadina line has escalated in cost from $2.1 billion to $2.6 billion, approximately $200 million of which can be attributed to stations, there is still $300 million unaccounted for. As a rough estimate, split amongst the remaining costs of the subway, it raises costs by 13%. This brings the cost to $86.2 million per km, very close to what the predictions for the Yonge extension estimate which includes difficult track configuration where crossing the East Don River. Important to note is the cost of structure without tunnelling using the same method of increasing costs proportionately on the Spadina estimate, which results in a cost of $22.6 million per km for at grade sections of construction, or approximately one quarter the cost of tunnelled track. This echoes the 2004 work of the International tunnelling Association, which studied projects to determine that in subway construction projects, median at grade construction cost 29% of what tunnelled construction did, with the average at 35%89.

Because we cannot derive cut and cover cost savings as a result of the TTC’s two extensions that have been studied, the estimate for that must come from the International tunnelling Association document. It has the median of cut and cover construction costing 68% of tunnelling, and the average cost being 84% of tunnelling. The reason there is a significant difference between the median and the average here is outlined in the document, noting that where land prices are high, tunnelling can actually be less expensive. Though relative to cities in the International tunnelling Association document Toronto’s land values are comparably cheap, much of the line will be constructed through the downtown core, and thus using the average rather than the median is probably closer to the expected costs of cut and cover in Toronto. Similarly, elevated track consistently costs approximately half of what tunnel bored construction costs. Because few sections of the line will be built in this manner, this selection of number will not be a major factor in the determination of costs for the line.


Methods and Stages of Construction

Major bridge crossings, such as would be required over the Don Valley, are much more difficult to determine the price of due to no similar bridges being required by the TTC, and bridge construction and length playing a major factor in the cost determination. The gap across the Don Valley is approximately 500m in length, which is comparable to the Saint John Harbour Bridge, of which a replacement was recently estimated at $150 million to construct28. A new bridge over the Ottawa River is estimated at $400-500 million for 1.5 km41. Probably closest in construction to the crossing of the Don Valley is the Park Bridge in British Columbia crossing the Kicking Horse Canyon, which is 404m in length, 80m high, and was constructed at a cost of $143 million118,95. It is therefore not unreasonable to expect a crossing of the Don Valley to register around $175 million. This estimate is higher than what those of the other bridges would infer, but it is intentionally so in order not to severely underestimate the costs of the project. Smaller crossings, such as a reconstruction of the Overlea bridge, would not be as significantly expensive.

Finally, other bridges, such as over small creeks or rivers, are much harder to determine information on how much track would cost. It would likely be similar to elevated tracks, but in order to not underestimate costs I will be using a figure of $100 million per kilometre for this document. This is based on the idea that as a worst-case scenario, a tunnel under the river that would likely be more expensive than regular tunnels due to engineering could be used. Since these bridges are so short and make up such an insignificant part of the overall line, even overestimating by double the cost would put the total estimates off by no more than 1% or so, well within the contingency of 25%.

The costs of constructing the tracks between stations in Toronto is as follows:

Construction Method Cost (in millions) per Kilometre
Major Bridging $350
Other Significant Bridging $100
Bored Tunnel $86.2
Cut and Cover $72.4
Elevated $43.1
At Grade $22.6


Engineering Costs

Though certain segments of the line should be relatively easy to construct, there is no doubt there will be a number of segments that will pose significant engineering challenges. Although the cost of engineering used by the Yonge line is almost three times higher than the Spadina line, rising costs on the Spadina line combined with the relative complexity of the Downtown Relief Line mean that engineering on the DRL will likely be somewhat pricey in certain segments. On others, however, tracks can run at grade and engineering is a lot less difficult. We will therefore use $80 million per km as a baseline for engineering costs for the Downtown Relief Line, with costs being adjusted slightly above or below that cost based on the complexity of the construction stage being evaluated. At grade segments will cost significantly less per km than complex tunnels.


Subway Yard Cost

A new subway maintenance and storage facility would need to be constructed as a result of any significant expansion in Toronto’s subway. In a November 2009 report, the TTC projected the cost of a new maintenance and storage facility slightly larger than the current Wilson yard for the Yonge line at $632 million175. Given the land value and availability around Yonge Street, it is doubtful that cost would be any higher for the proposed location of a subway yard at the former Lever Brothers factory at base of the Don River. For the purposes of this cost estimation, $632 million will be added for the provision of a new subway yard.


Rolling Stock

Using the Spadina extension’s determination of 56 new subway cars for an 8.6 km line means that roughly 6.5 cars per kilometre of new subway are required. One of the new Toronto Rocket cars currently costs $3 million22. Thus, $19.5 million becomes the price per kilometre necessary for rolling stock.


Property Acquisition

Property acquisition is required for stations and when the track runs in an above ground right-of-way. It is not needed when the track passes below property at a depth that it does not cause disturbance to the buildings above105. Higher property costs for stations in the downtown can be offset by the lack of need for bus terminals, and the ability to convince property owners of the value of a direct entrance from the subway to their building, integrating the entrances into existing or proposed properties rather than needing a property for only the station itself.


Contingency

A contingency cost equal to 25% of the total will be added to cost of the estimation, not including property or rolling stock.

 

Cost Estimates for Stage One of Construction. Cityplace (Spadina) to Wynford (Eglinton)

Stations

Stage One of construction will be the most expensive, posing the greatest challenges from an engineering perspective, having only a minimal part of track at grade level, requiring the crossing of the Don Valley and very deep tunnelling through the downtown core. Additionally, the cost of the subway yard will be included in the cost of Stage One, while it will not be necessary for future stages.

Stage One consists of thirteen stations. From southwest to northeast, they are as follows:

Station Name Location
Cityplace Spadina Ave. and Bremner Blvd.
Rogers Centre Rees St. and Bremner Blvd.
Financial District Bay St. and Wellington St. W
St. Lawrence Jarvis St. and The Esplanade
Parliament Parliament St. and Mill St.
Cherry Cherry St. and Mill St.
Queen East CN Kingston Tracks and Queen St. E
Gerrard Carlaw Ave. and Gerrard St. E
Danforth/Pape Pape Ave. and Danforth Ave.
Cosburn Pape Ave. and Cosburn Ave.
Thorncliffe Park 48 Thorncliffe Park Dr.
Flemingdon Park Don Mills Rd. and Gateway Blvd.
Wynford Don Mills Rd. and Eglinton Ave. E

The positives in terms of station cost estimation are that Wynford and Cherry are the only stations that would require further expenditure in terms of a bus platform and commuter parking in the case of Wynford, and a streetcar transfer platform in the case of Cherry. All other stations would serve passengers through a walkup model with transfers potentially required if a smart card system still is not operational.

The expensive side of these stations comes in terms of the three most southeasterly stations, which must be extraordinarily deep by Toronto’s standards in order to tunnel under other subways, utilities, the PATH network, and building foundations. In terms of depth, they may reach the point at which it becomes more economically feasible to construct them using tunnel boring machines rather than the traditional method of cut and cover for stations, as stations deeper than 30m underground become cheaper to construct with a tunnelling method36. Between the standard depth of 15m and 30m, cost increases by $1.9 to 2.2 million per metre of depth. Specifically, the Financial District station must not only be deep, but additional costs will occur due to the likely necessity to upgrade PATH tunnels that connect Union, St. Andrew and King stations to allow for transfers.


Track


Pape Village

From the southwest, the track will begin at Cityplace station from around Bathurst and the railway tracks. From there, it will be constructed deep underground using a tunnel boring machine for 2.3 km to St. Lawrence station, reaching a maximum depth of 30-35 metres underground west of Financial District station. From St. Lawrence, it will be constructed as cut and cover for 700m along The Esplanade, where again tunnelling will be used for 1 km to a point just west of the Don River, where the track will come above ground, cross the Don River on a small new bridge, and run at grade for 1.9 km to just past Gerrard, where it will again enter a tunnel. This tunnel will run for 3.4 km to the intersection of Pape and Donlands, where a new bridge of 500m will need to be constructed to carry the subway across the Don Valley. Upon reaching the other side of the Don Valley, construction again will tunnel under Thorncliffe Park where it will continue for 700m to the western edge of the Don Valley, behind the towers on the eastern side of Thorncliffe Park. Track will run at grade for 400m before joining Overlea Blvd. and recrossing the valley on a rebuilt Overlea Blvd bridge 200m in length. From that point, construction will remain tunnelled to the end of the line 1.6 km away, at Wynford station. Tail tracks are not included in this estimate as they are included in the costs of the terminal stations. Bridges may need to be widened when following the railway corridor to accommodate the extra tracks.

Type of Track Total Length
Tunnelled 9,000m
Cut and Cover 700m
At Grade 2,300m
Major Bridges 500m
Significant Bridges 200m
Total Length of Revenue Track 12.7 km

Stage One Cost

The cost of Stage One is therefore estimated to be as follows:

Project Element Cost
Cityplace Station $200,000,000
Rogers Centre Station $145,000,000
Financial District Station $175,000,000
St. Lawrence Station $120,000,000
Parliament Station $110,000,000
Cherry Station $150,000,000
Queen East Station $30,000,000
Gerrard Station $30,000,000
Danforth/Pape Station $130,000,000
Cosburn Station $115,000,000
Thorncliffe Park Station $120,000,000
Flemingdon Park Station $115,000,000
Wynford Station $180,000,000
Tunnels, special structures and operating systems $1,073,000,000
Subway Trains $247,650,000
Storage and Maintenance Facilities for subway trains $632,000,000
Engineering and other costs $1,300,000,000
Property $292,000,000
Contingency Costs (25%) $1,156,250,000
GST Rebate ($353,970,400)
TOTAL $5,966,929,600

This estimate of $5.95 billion for the line, or $470 million per kilometre, may seem high but is probably in line with the difficult engineering involved with routing a subway downtown that does not always follow major roads.
It is worth noting a number of points in regards to this figure. First, when estimating costs, they were generally estimated to be on the high rather than on the low side of ranges. Secondly, this is by far the most expensive segment of the line involving the most complex engineering and absorbing the cost of a new rail yard. Finally, this cost does not factor out the savings of various costly improvements that would need to be built on the Yonge line if the Downtown Relief Line does not get built. Councillor Michael Thompson estimates these costs to be between $2.46-4.67 billion139. If these estimates are right, the actual expansion cost of Stage One of the Downtown Relief Line can be seen as $1.33-3.54 billion, or between $105 and $279 million per kilometre, a relative bargain by Toronto’s current standards.

The main problem is that although these estimates may appear expensive, the cost will only continue to climb for a piece of infrastructure which is undoubtedly necessary for the long-term health of a city that as of 2010 has one of the worst commutes on the planet69.

 

Cost Estimates for Stage Two of Construction. Cityplace (Spadina) to Dundas West

Stations

Stage Two of construction will be relatively cheap, being able to stay at grade for most of the construction so long as the potential development of the Downtown Relief Line is accounted for when the Georgetown Rail Corridor is reconstructed.

Stage Two consists of eight stations. From southeast to northwest, they are as follows:

Station Name Location
Cityplace Spadina Ave. and Bremner Blvd.
Fort York Bathurst St. and Fort York Blvd.
Strachan Strachan Ave. and GO Weston Tracks
Liberty Village GO Weston Tracks and King St. W
Gladstone Dufferin St. and Queen St. W
MacDonell Lansdowne Ave. and CN Weston Tracks
Sorauren GO Weston Tracks and Dundas St. W
Dundas West Dundas St. W and Bloor St. W

Though running through the rail corridor, many of these stations must be below ground as a result of the Georgetown Rail expansion.


Track

From the southeast, the track will begin where the tailtracks from Cityplace station left off from around Bathurst and the railway tracks. From there, the tracks will tunnel 600m under the GO Lakeshore Line and continue as a bored tunnel for 2.9 more km to a point slightly beyond MacDonell station. There, they emerge in the railway corridor where more space exists than further south to continue 1.5 km to Dundas West Station. Tail tracks are not included in this estimate as they are included in the costs of the terminal stations.

Type of Track Total Length
Tunnelled 3,500m
At Grade 1,500m
Total Length of Revenue Track 5.0 km

Stage Two Cost

The cost of Stage Two is therefore estimated to be as follows:

Project Element Cost
Fort York Station $120,000,000
Strachan Station $150,000,000
Liberty Village Station $150,000,000
Gladstone Station $160,000,000
MacDonell Station $150,000,000
Sorauren Station $35,000,000
Dundas West Station $50,000,000
Tunnels, special structures and operating systems $335,600,000
Subway Trains $97,500,000
Engineering and other costs $250,000,000
Property $120,000,000
Contingency Costs (25%) $350,150,000
GST Rebate ($110,222,000)
TOTAL $1,858,028,000

$1.85 billion, or $372 million per km, will get us a western section of the Downtown Relief Line to allow passengers traveling from the west a quicker journey downtown, as well as provide important service to Parkdale and Liberty Village. Though this estimate may be high, it is expected that station costs must be higher than average in order to accommodate the construction of them without using cut and cover construction, to avoid disruption to the rail corridor above.

 

Cost Estimates for Stage Three of Construction. Wynford (Eglinton) to Sheppard/Don Mills

Stations

Stage Three of construction will be relatively cheap, being able to stay at grade for most of the construction so long as the potential construction of the Downtown Relief Line is accounted for when the Georgetown Rail Corridor is reconstructed.

Stage Three consists of four stations. From south to north, they are as follows:

Station Name Location
Wynford Don Mills Rd. and Eglinton Ave. E
The Donway Don Mills Rd. and Lawrence Ave. E
Moatfield Don Mills Rd. and York Mills Rd.
Sheppard/Don Mills Don Mills Rd. and Sheppard Ave. E

Stations not already constructed (The Donway and Moatfield) will have a small bus terminal. A terminal already exists at Sheppard/Don Mills as does commuter parking.


Track

Track will be tunnelled the entire 5.7 km length of the line from the tail tracks at Wynford to Sheppard/Don Mills Station. Tail tracks are not included in this estimate as they are included in the costs of the terminal stations.

Type of Track Total Length
Tunnelled 5.7km
Total Length of Revenue Track 5.7 km

Stage Three Cost

The cost of Stage Three is therefore estimated to be as follows:

Project Element Cost
The Donway Station $140,000,000
Moatfield Station $140,000,000
Sheppard/Don Mills Station $130,000,000
Tunnels, special structures and operating systems $491,340,000
Subway Trains $111,500,000
Engineering and other costs $427,500,000
Property $45,000,000
Contingency Costs (25%) $332,210,000
GST Rebate $83,179,040
TOTAL $1,900,729,040

$1.9 billion, or $333 million per km, will connect the Downtown Relief Line with the Sheppard Subway, the Sheppard East LRT, and potentially the Finch West LRT, forming a major transit hub at Sheppard/Don Mills. This will give a huge boost in terms of network connectivity and taking even more riders off the Yonge subway.

 

Cost Estimates for Stage Four of Construction. Dundas West to Pearson Airport

Stations

Stage Four of construction will finish the Downtown Relief Line, providing an alternate route to Eglinton to the airport which brings rapid transit closer to the dense and underserved communities of Weston and North Etobicoke, while providing a more direct path to the airport along Dixon Road, hitting some important trip generators.

Stage Four consists of thirteen stations. From southeast to northwest, they are as follows:

Station Name Location
Dundas West Dundas St. W and Bloor St. W
Junction GO Weston Tracks and Dupont Ave.
Stock Yards GO Weston Tracks and St. Clair Ave. W
Rogers Road GO Weston Tracks and Rogers Rd.
Black Creek GO Weston Tracks and Eglinton Ave. W
Denison Jane St. and GO Weston Tracks
Weston GO Weston Tracks and Lawrence Ave. W
Scarlett Scarlett Rd. and Dixon Rd.
Islington North Islington Ave. and Dixon Rd.
Kipling North Kipling Ave. and Dixon Rd.
Highway 27 Highway 27 and Dixon Rd.
Carlingview Carlingview Dr. and Dixon Rd.
Pearson International Airport Pearson - Above the Terminal 1 People Mover

Stations along this part of the line vary in complexity, but none will require expansive bus bays or extreme engineering techniques. Some will be at grade, others below ground, and a few elevated.


Track


The Neighbourhood of Weston

From the southeast, the track will begin where the tailtracks from Dundas West station left off. From there, the tracks will remain at surface for approximately 800m to a point just beyond Junction station. From there, they will enter a brief 700m tunnel to get underneath the railway junction, after which they will emerge back at grade to travel for 1.7 km to Black Creek Dr., where a bridge will carry the tracks 250m before reemerging at grade for 3.25 km to just beyond Weston station. From there, they will enter a brief tunnel at John St, curving west to Fern Ave. and Weston Rd 600m away, where the tracks will briefly appear above ground to bridge over the Humber River for 200m. The tracks then enter back underground, using cut and cover along the length of Dixon 4.5 km until leaving Highway 27 station, just east of Highway 27. There the tracks become elevated and run that way 3 km to Pearson Airport. Tail tracks are not factored into the calculation as they are already included in terminal stations. Cut and cover is used along Dixon to save costs due to the width of Dixon and minimal businesses making cut and cover construction minimally disruptive. Elevated track is chosen west of Dixon to further decrease costs and due to a lack of residential housing and airport related land uses which minimize development potential.

Type of Track Total Length
Tunnelled 1,300m
Cut and Cover 4,500m
Elevated 3,000m
At Grade 5,750m
Significant Bridges 450m
Total Length of Revenue Track 15.0 km

Stage Four Cost

The cost of Stage Four is therefore estimated to be as follows:

Project Element Cost
Junction Station $30,000,000
Stock Yards Station $40,000,000
Rogers Road Station $30,000,000
Black Creek Station $40,000,000
Denison Station $30,000,000
Weston Station $35,000,000
Scarlett Station $120,000,000
Islington North Station $115,000,000
Kipling North Station $115,000,000
Highway 27 Station $145,000,000
Carlingview Station $50,000,000
Pearson International Airport Station $95,000,000
Tunnels, special structures and operating systems $742,110,000
Subway Trains $292,500,000
Engineering and other costs $750,000,000
Property $200,000,000
Contingency Costs (25%) $584,277,500
GST Rebate ($191,177,700)
TOTAL $3,222,709,800

$3.2 billion, or $215 million per km, will get us a route to the airport, a subway through some of the highest density areas of the city, and much closer transit to Weston and North Etobicoke.

 

Combined Cost

The total cost of all stages of this proposal is $12.9 billion for 39.9 km of revenue track. If the City of Toronto builds one kilometre a year on average, the cost would be $323 million per year to make a significant change in our subway system by 2050. Speeding up the implementation to 2030 to try to avoid even further cost escalation and get these important routes constructed means a yearly cost of $646 million. A notable portion of these costs will be required regardless of whether or not the Downtown Relief Line is built in order to relieve congestion on the Yonge subway. The longer we wait the more these costs continue to grow, which is why it is imperative that construction on the Downtown Relief Line begin as soon as possible.

 

Image Sources

From top to bottom:

© 2010 Phil Orr & Andrew Perry